Title V New Applicants and Renewals

Newly constructed Title V facilities have 12 months from start of operation to submit a Title V Permit Application. Additionally, the facility must submit an operating permit request 15 days after initial startup of any process ( S.C. Regulation 62.1, Section II). Title V modification forms are used once the facility has been issued the Title V permit.

For sources that already have a Title V Operating Permit, your facility must submit a Title V operating permit renewal application to the BAQ at least six months prior to the date of permit expiration. To allow time for the Department to review your application for completeness and obtain any additional information needed, we strongly recommend that applications be submitted 90 days prior to this deadline.