Dominion Carolina Gas Transmission, LLC

DHEC has received information related to two (2) pipeline projects proposed by Dominion Carolina Gas Transmission, LLC. On January 29, 2016, DHEC issued a Notice of General Public Interest to notify the public of DHEC permitting/certification decisions related to these proposed projects.

Transco to Charleston

Dominion Carolina Gas Transmission is proposing to construct and/or modify and operate the Transco to Charleston Project. The proposed Transco to Charleston Project will include approximately 60 miles of pipeline including two new natural gas transmission pipelines, upgrades to an existing compressor station, and the addition of a new compressor station.

Below is a list of permits that may be required by DHEC for the proposed Transco to Charleston project, and pertinent related information. Additional details about the project may be found at Dominion Carolina Gas Transmission's Transco to Charleston website.

On March 21, 2017, DHEC hosted a drop-in to share information about the Moore to Chappells portion of the proposed project.  DHEC staff provided a brief presentation on the 401 water quality certification review process for the proposed pipeline.  DHEC staff and company representatives also addressed various topics, such as regulatory and permit requirements for natural gas pipelines, natural gas pipeline construction, safety and maintenance, and natural gas needs, at information stations.

Project Name

Affected County(ies)

Permit Type

Application Received

Final Permit Action

Point of Contact

 

 

Moore to Chappells Pipeline

 

 

Spartanburg, Laurens, Newberry, Greenwood

Hydrostatic Test Water Discharge General Permit

October 18, 2016
Notice of Intent

April 11, 2017

Brett Caswell
803-898-4396

Stormwater Construction Permit

May 23, 2016

(February 2, 2017 FERC approval exempts state permit)

Shawn Clarke
803-898-3544

401 Water Quality Certifications or
Navigable Waters Permit

September 23, 2016

April 11, 2017
Public Notice of Department Decision

April 27, 2017
Final Certification

Chuck Hightower
803-898-0369

Moore Compressor Station

Spartanburg

Air Construction Permit

December 21, 2015

April 8, 2016

Michael Robertson 
803-898-1236

 

 

 

Dillon Pipeline

 

 

 

Dillon

Hydrostatic Test Water Discharge General Permit

May 12, 2016

August 1, 2016

Brett Caswell
803-898-4396

Stormwater Construction Permit

May 4, 2016

(February 2, 2017 FERC approval exempts state permit)

Shawn Clarke
803-898-3544

401 Water Quality Certifications or Navigable Waters Permit

May 16, 2016

May 26, 2016

Chuck Hightower
803-898-0369

Dorchester Compressor Station

Dorchester

Air Construction Permit

December 21, 2015

April 8, 2016

Wanda Parnell 
803-898-1296

Charleston Town Border Station

Charleston

Coastal Zone Consistency Certification

 

April 21, 2016

Curtis Joyner
843-953-0205

Columbia-to-Eastover

Dominion Carolina Gas Transmission also requested permits to build a natural gas pipeline in Richland and Calhoun counties to transport natural gas to the International Paper Eastover facility to fuel its boilers. The proposed pipeline will be approximately 29 miles long to reach the facility.

Below is a list of permits required by DHEC for the Columbia-to-Eastover pipeline project, and pertinent related information. Additional details about the project may be found at Dominion Carolina Gas Transmission's Columbia to Eastover website.

Permit Type

Application Received

Final Permit Action

Point of Contact

Hydrostatic Test Water Discharge General Permit

November 6, 2015
Plans

April 21, 2016

Brett Caswell
803-898-4396

401 Water Quality Certifications or

Navigable Waters Permit

June 9, 2016






September 15, 2016

June 20, 2016
(401 Water Quality Certification)

June 21, 2016
(Navigable Waters Permit)

September 20, 2016

Chuck Hightower
803-898-0369

Stormwater Construction Permit


December 8, 2015

May 18, 2016

Cynthia Ashford
803-898-3995

Paul Quattlebaum
803-898-3678