May 29, 2013 - The leachate treatment system has begun operation and an operating permit was issued for the system.

May 23, 2012 - Construction and operation of a new on-site leachate treatment system has been approved. The construction permit was issued on May 23, 2012. The leachate treatment system will consist of metals precipitation, a filter press, an evaporator, and sludge and slurry dryers. Construction of the on-site leachate collection and treatment system will take 6-9 months.