Permitting Capacity of Wastewater Treatment Plants
A Plan for Tracking Capacity of Domestic Systems


clarifierDHEC issues discharge permits (e.g., NPDES) for wastewater treatment plants. For domestic items, these permits have limits for flow. The NPDES permit flow limit would relate to the facilities available to treat the wastewater arriving at the plant. For example, a plant that could treat 5 MGD would have a flow limit of 5 MGD.

At any given time, the actual flows at a plant would typically be less than its design capacity. Cities are constantly adding new collection systems to accommodate residential, commercial and industrial growth. For our hypothetical 5 MGD plant, it would not be surprising to see it flowing at 3 MGD on average. At this point, we have defined two concepts: Design flow and actual flow. To track true available capacity, DHEC identifies another concept: permitted capacity or obligated capacity.

treatment plant capacity chartBeyond actual flow, flow has been obligated via the issuance of new sewer collection system permits. The day DHEC issues such permits the flow has been obligated so DHEC accounts for this flow. For example, our 5 MGD plant may be flowing at 3 MGD, but permits have been issued for new collection systems that have yet to be fully utilized. In the case of a residential subdivision, even a couple of years after the permit has been issued, all of the lots may not have been built on and therefore the flow has yet to be fully realized. Therefore, it would be typical that the permitted flow to a treatment plant would be in between the actual flow and design capacity of the plant (see chart). In this example, the cumulative permitted flow is 3.5 MGD.

When do we stop permitting? DHEC issues sewer collection system permits until the permitted capacity (obligated flow) reaches the design capacity of the plant. Prior to that, DHEC typically notifies the plant owner when the permitted flow reaches 80% of the design capacity. In this notification, the utility is asked to submit a Preliminary Engineering Report (PER) to address their plans for additional capacity.

More Information? For more information on DHEC's program to track capacity in wastewater treatment facilities, please contact Jeff deBessonet at 803-898-4157.